Building Safety Act Golden Thread
Description
Setup of Golden Thread on Box Hubs (RIBA 0-1)
At Stage 0-1 a project file is created to manage documentation for all projects or change to spaces, infrastructure and services. A standardised structure is set up on 51³Ô¹ÏÍø's Box cloud storage portal to enable the Property Division to collaborate internally and externally on projects. For minor works, a simplified folder structure is available upon request.
- The Project Manager (PM) contacts the Estates Records & Archives Officer to request a project file as soon as records are being created. This shouldn't wait until a potential project/change is approved as early-stage records may be revisited at another stage in the future and should be held in a managed system.
- To register a project file, the following information is required: Location of works (room/floor level/building), Suggested project title, Access requirements (anyone outside the Property Division who needs access at this stage).
- The registed project file is handed over to the PM who is then responsible for managing access and maintaining content.
- The project number is to be used on all documentation and communication. For confidential early-stage information, contact the Estates Records & Archives Officer for advice on an interim storage location
- Folder and file names must be clear and concised, with minimal use of multiple nested sub-folders. Refer to the Divisional Record Document guidelines for further advice.
Engagement
- PM to ensure project team have access to the Collaboration sub-folder
- PM to notify the Estates Records & Archives Officer of any changes to the project scope or title
- External PM to receive induction/training on 51³Ô¹ÏÍø's project filing in Box with the Estates Records & Archives Officer
Forms & Links
- Project Filing Structure:
- Property Division Box Guidelines:
- Minor Works Project Filing Structure:
- Records Retention Schedule: *Note this is held by ACRU/Central Governance, not Property -
Approvals & Compliance Review
Estates Records & Archives Officer to carry out random audits of project filing and contact the Project Manager if folders need to be populated.
Repeated Subsequent RIBA Stages
RIBA Stage 2
Where an External PM has been appointed, the Imperail PM is to give access to the PM + QS / Collaboration sub-folders within the project file. Schedule an induction meeting with the Estates Records & Archives Officer for guidance on Box and project filing best practice. PM to give the Design Team and any 51³Ô¹ÏÍø stakeholders outside of the Property Division access to the Collaboration sub-folder on the project file. (Viewer/Uploader access unless there is an essential requirement for Editor level access).
At End-of-Stage, PM is to ensure the Box project file has been fully populated, with any information held elsewhere uploaded.
RIBA Stage 3
At End-of-Stage, PM is to ensure the Box project file has been fully populated, with any information held elsewhere uploaded.
RIBA Stage 4
At End-of-Stage, PM is to ensure the Box project file has been fully populated, with any information held elsewhere uploaded.
RIBA Stage 5
PM to give Contractor access to the Collaboration sub-folder within the project file (Viewer/Uploader access). If requested by the Contractor, PM to give the Technical Author access to the Collaboration sub-folder of the project file (Viewer/Uploader access).
At End-of-Stage, PM is to ensure the Box project file has been fully populated, with any information held elsewhere uploaded.
RIBA Stage 6
On completion, PM is to ensure the Box project file has been fully populated, with any information held elsewhere uploaded. Project Manager to remove access to project team as required.
RIBA Stage 7
At defects end, when the project is finally closed, the PM notifies the Estates Records & Archives Officer and ensures that all external collaborators have had their access removed. Estates Records & Archives Officer transfers the closed project file to a holding area to review for archive retention, extracting any information required for long-term access or inclusion in the Golden Thread as applicable.
The remainder of the project file is moved to secure storage for the required retention period as per 51³Ô¹ÏÍø's retention schedule.